Question:
A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day, Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?
Answer:

Penalty given for first day= 200

Penalty given for second day = 250

Penalty given for third day = 300

Every day penalty increase = 50

It forms an arithmetic series. 

Now

first term a = 200

common difference d = 50

Total number of terms = 30 (because we have to calculate penalty for 30 days)

Now sum 30 terms of AP = (n/2) *{2a + (n-1)*d}

                                    = (30/2)*{2*200 + (30-1)*50}

                                    = 15*(400 + 29*50)

                                    = 15*(400 + 1450)

                                    = 15*1850

                                    = 27750

So total penalty for 30 days = 27750 rupees

Not what you are looking for? Go ahead and submit the question, we will get back to you.

learnohub

Classes

  • Class 6
  • Class 7
  • Class 8
  • Class 9
  • Class 10
  • Class 11
  • Class 12
  • ICSE 6
  • ICSE 7
  • ICSE 8
  • ICSE 9
  • ICSE 10
  • NEET
  • JEE

YouTube Channels

  • LearnoHub Class 11,12
  • LearnoHub Class 9,10
  • LearnoHub Class 6,7,8
  • LearnoHub Kids

Overview

  • FAQs
  • Privacy Policy
  • Terms & Conditions
  • About Us
  • NGO School
  • Contribute
  • Jobs @ LearnoHub
  • Success Stories
© Learnohub 2026.